Milestone Projects River Crossings Creek Crossings Lake Crossings |
Road Crossings Rail Crossings Trenchless HDD Intersects (Shallow) Trenchless HDD - Notable Projects |
Milestone Projects |
River Crossings
PROJECT | NPS | INSTALLATION LENGTH | CASING LENGTH | FINAL HOLE DIAMETER | GEOLOGIC FORMATION | HDD APPLICATION |
Athabasca - Intersect | 6+6+6 | 1,278m | 37m | 24" | Sandstone | Mud Motor |
Battle River | 8 | 846m | 51mn/a | 12" | Sandstone | Mud Motor |
Blind Man River | 6 | 341m | n/a | 12" | Shale | Air Hammer |
Bow River - Intersect | 16 | 957m | 48m | 24" | Shale | Intersect |
Brazeau River | 6 | 506m | n/a | 10" | Sandstone | Air Hammer |
Burland River | 8 | 844m | 66m | 12" | Shale | Mud Motor |
Chichaga River | 10 | 502m | 57m | 16" | Mudstone | Mud Motor |
Clearwater River | 12 | 1,066m | 14 | 20" | Sandstone | Mud Motor |
Cut Bank River | 16 | 443m | n/a | 24" | Sandstone | Air Hammer |
Edson River | 4 | 612m | n/a | 8" | Sandstone | Air Hammer |
Goose River | 6 | 712m | n/a | 12" | Till | Jetted |
Iosegun River - Intersect | 24 | 1,109m | 84m | 32" | Shale | Mud Motor |
Kakwa River | 10 | 1,311m | 73m | 16" | Shale / Sandstone | Mud Motor |
Keg River | 10 | 683m | 45m | 16" | Shale | Mud Motor |
Little Smokey River - Intersect | 8+8+8 | 1,492m | n/a | 24" | Till | Jetted |
Loon River | 6 | 707m | n/a | 12" | Till / Clay | Jetted |
Mcleod River | 12 | 351m | 10m | 20" | Mudstone | Mud Motor |
Muskeg River | 12 | 361m | n/a | 18" | Mudstone | Air Hammer |
Nordegg River | 6 | 687m | n/a | 12" | Sand / Sandstone | Air Hammer |
North Saskatchewan River - Intersect | 12 | 1,208m | 34m | 20" | Shale / Sandstone | Mud Motor |
Old Man River - Intersect | 8 | 1,414m | 49m | 16" | Sandstone | Mud Motor |
Pembina River | 10 | 739m | 55m | 16" | Shale | Mud Motor |
Red Deer River | 16 | 632m | 32m | 24" | Shale | Mud Motor |
Simonette | 12 | 1,648m | 94m | 20" | Sandstone | Mud Motor |
Smokey River - Intersect | 8+8+8 | 1,833m | 137m | 24" | Mudstone | Mud Motor |
Creek Crossings
PROJECT | NPS | INSTALLATION LENGTH | CASING LENGTH | FINAL HOLE DIAMETER | GEOLOGIC FORMATION | HDD APPLICATION |
Ante Creek | 24 | 336m | 22m | 30" | Mudstone | Mud Motor |
Attikkamek Creek | 16 | 467m | n/a | 24" | Till | Jetted |
Big Mountain Creek | 12 | 511m | n/a | 20" | Till | Jetted |
Bird Creek | 8 | 586m | 37m | 12" | Sandstone | Mud Motor |
Black Mud Creek - Intersect | 30 | 738m | n/a | 42" | Till | Jetted |
Carrot Creek | 6 | 393m | n/a | 12" | Till | Jetted |
Chickadee Creek | 12 | 208m | n/a | 24" | Till | Jetted |
Deep Valley Creek - Intersect | 10 | 1,164m | n/a | 16" | Sandstone | Air Hammer |
Dilly Creek | 24 | 447m | n/a | 36" | Till | Jetted |
Dismal Creek | 8+8+8 | 712m | n/a | 24" | Sandstone | Jetted |
Farrell Creek | 16 | 540m | n/a | 24" | Shale | Air Hammer |
Fish Creek | 20 | 404m | n/a | 32" | Till | Jetted |
Fox Creek | 8 | 266m | n/a | 16" | Till | Jetted |
Gunderson Creek | 12 | 250m | n/a | 24" | Sandstone | Air Hammer |
Hines Creek | 6 | 381m | n/a | 12" | Till | Jetted |
Lambert Creek - Intersect | 6 | 998m | n/a | 12" | Till | Jetted |
Lobster Creek - Intersect | 12 | 784m | n/a | 20" | Till | Jetted |
Marsh Head Creek - Intersect | 8 | 630m | n/a | 12" | Shale | Air Hammer |
Nose Creek | 24 | 145m | n/a | 36" | Till | Jetted |
Patterson Creek | 8 | 517m | n/a | 14" | Till | Jetted |
Pine Creek | 4 | 341m | 29m | 8" | Sandstone | Mud Motor |
Pinto Creek | 16 | 648m | n/a | 24" | Till | Jetted |
Prairie Creek | 4 | 434 | n/a | 8" | Till | Jetted |
Priddis Creek | 6 | 357m | 17m | 12" | Shale | Mud Motor |
Sheep Creek | 10 | 678m | 33m | 16" | Shale | Mud Motor |
Sulphur Creek - Intersect | 8+8+8+8 | 950m | TS | 32" | Weak Shale | Mud Motor |
Two Creeks | 12 | 896m | 51m | 20" | Sandstone | Mud Motor |
Wapiti Creek - Intersect | 4 | 673m | 36m | 8" | Sandstone | Air Hammer |
Windfall Creek | 4 | 419m | n/a | 8" | Till | Jetted |
Wolf Creek | 10 | 531m | n/a | 18" | Till | Jetted |
Lake Crossings
PROJECT | NPS | INSTALLATION LENGTH | CASING LENGTH | FINAL HOLE DIAMETER | GEOLOGIC FORMATION | HDD APPLICATION |
Kiskitaw Lake | 16 | 948m | 94m | 24" | Sandstone | Mud Motor |
Loon Lake | 4 | 711m | n/a | 12" | Till | Jetted |
Peppers Lake | 6 | 899m | n/a | 12" | Till | Jetted |
Saunders Lake - Intersect | 10 | 714m | 17m | 18" | Till | Mud Motor |
Weed Lake - Intersect | 24+24 | 1,164m | n/a | 36" | Clay | Jetted |
Road Crossings
PROJECT | NPS | INSTALLATION LENGTH | CASING LENGTH | FINAL HOLE DIAMETER | GEOLOGIC FORMATION | HDD APPLICATION |
17th St. NE, Edmonton | 12 | 186m | n/a | 24" | Till | Jetted |
45th St. Leduc - Intersect | 10 | 814 | n/a | 18" | Mixed | Air Hammer |
Sparrow Drive | 10 | 769m | 18m | 16" | Mudstone | Mud Motor |
9th St. NE, Edmonton | 12 | 636m | n/a | 24" | Clay / Till | Jetted |
Confederation Way | 24 | 208m | n/a | 36" | Clay / Till | Jetted |
Crowchild Trail | 10 | 317m | n/a | 16" | Clay / Till | Jetted |
Deerfoot Trail | 16 | 737m | n/a | 24" | Clay / Till | Jetted |
Highway 16 | 12 | 886m | n/a | 20" | Clay / Till | Jetted |
Highway 2 | 8 | 336m | n/a | 16" | Clay / Till | Jetted |
Highway 21 | 24 | 220m | n/a | 32" | Clay / Till | Jetted |
Highway 40 | 10 | 474m | n/a | 16" | Clay / Till | Jetted |
Highway 43 - Intersect | 16 | 791m | 44m | 24" | Mudstone | Mud Motor |
Highway 63 | 12 | 306m | n/a | 18" | Clay | Jetted |
John Laurie Blvd., Calgary | 12 | 184m | n/a | 18" | Clay | Jetted |
MacLeod Trail, Calgary | 16 | 303m | n/a | 24" | Clay | Jetted |
McKnight Blvd., Calgary | 10 | 362m | n/a | 16" | Clay | Jetted |
Meridian St., Edmonton | 12 | 168m | 14m | 18" | Sandstone | Mud Motor |
Peigan Trail, Calgary | 10 | 464m | n/a | 16" | Clay Shale | Jetted |
Stoney Trail | 12 | 370m | 19m | 20" | Clay Shale | Air Hammer |
Rail Crossings
PROJECT | NPS | INSTALLATION LENGTH | CASING LENGTH | FINAL HOLE DIAMETER | GEOLOGIC FORMATION | HDD APPLICATION |
CN Terminal - 11 Active Rail Crossing | 24 | 453m | n/a | 32" | Cobble | Jetted |
Transportation Utility Corridor (TUC) - 47 Pipeline / 2 Rail | 12 | 917m | n/a | 18" | Till | Jetted |
Transportation Utility Corridor (TUC) - 14 Pipeline / 2 Rail | 8 | 272m | n/a | 16" | Till | Jetted |
Trenchless HDD Intersects (Shallow Intersects)
PROJECT | NPS | INSTALLATION LENGTH | CASING LENGTH | FINAL HOLE DIAMETER | GEOLOGIC FORMATION | HDD APPLICATION |
CIOC - Gold Creek; Segment 3 | 8 | 3,217m | n/a | 18" | Glacial Till | Jetted |
MMS - RMP Mainline | 10 | 3,081m | surface 14m | 20" | Clay | Jetted |
MMS - RMP Mainline | 6 | 3,081m | surface 11m | 16" | Clay | Jetted |
MMS - Northern Loop | 10 | 3,008m | n/a | 20" | Clay | Jetted |
HHR - South Gathering | 8 | 2,991m | surface 10m | 24" | Muskeg / Sand | Jetted |
MMS - Gold Creek | 12 | 2,768m | n/a | 24" | Muskeg / Sand | Jetted |
CIOC - Gold Creek; Segment 3 | 6 | 2,661m | surface 8m | 18" | Glacial Till | Jetted |
CIOC - Gold Creek; Segment 3 | 8 | 2,664m | n/a | 20" | Clay / Muskeg | Jetted |
Pembina - Cloverbar Replacement | 12 | 2,293m | surface 12m | 24" | Glacial Till | Jetted |
HHR - Hammerhead Mainline | 8 | 2,114m | n/a | 24" | Clay / Sand | Jetted |
Trenchless HDD - Notable Projects
PROJECT | NPS | INSTALLATION LENGTH | CASING LENGTH | FINAL HOLE DIAMETER | GEOLOGIC FORMATION | HDD APPLICATION |
CIOC - Smokey River Valley | 8+8+8 | 4,147m | n/a | 12+12+12 | Clay / Glacial Till | Jetted |
Parks Canada - Elk Island National Park | 4 | 14,481m | n/a | 8" | Clay / Glacial Till | Jetted |
Cadence Energy - Gathering Replacement | 3+4+6 | 117,844m | n/a | 6+8+10 | Clay / Glacial Till | Jetted |
Kereco Energy - Gathering Replacement | 3+4+6 |
166,417m | n/a | 6+8+10 | Clay / Glacial Till | Jetted |
Barrick Energy - Gathering Replacement | 3+4+6 |
89,746m | n/a | 6+8+10 | Clay / Glacial Till | Jetted |
Canadian Forest Oil - Mainline Construction | 4+6 | 21,546m | n/a | 6+8 | Clay / Glacial Till | Jetted |
Pinecrest Energy - Gathering & Mainline | 3+4+6+8 | 147,764m | n/a | 6+8+10 | Clay / Glacial Till | Jetted |
Lone Pine Resources - Gathering & Mainline | 3+4+6+8 |
201,876m | n/a | 6+8+10 | Clay / Glacial Till | Jetted |
Devon Canada - Produced Water System | 4+6+8 | 22,774m | n/a | 8+12+16 | Clay / Glacial Till | Jetted |
CIOC - Gold Creek / KARR Gathering & Mainlines | 4+6+8+10+12 | 354,351m | n/a | 8+20 | Clay / Glacial Till | Jetted |
HHR - Gold Creek / KARR Gathering & Mainlines | 4+6+8+10+12 |
210,874m | n/a | 8+20 | Clay / Glacial Till | Jetted |
MMS - Gold Creek / KARR Gathering & Mainlines | 6+8+10+12 |
76,740m | n/a | 8+20 | Clay / Glacial Till | Jetted |
Pembina Pipelines - Marsh Head Creek Replacement | 12 | 16,184m | n/a | 24" | Clay / Glacial Till | Jetted |
Pembina Pipelines - Cloverbar TUC & Line Lowering | 12 | 5,646m | n/a | 24" | Glacial Till | Jetted |
LPR - Source Water Mainline | 24 | 27,640m | n/a | 32" | Clay / Glacial Till | Jetted |
Westlock, AB - Produced Water Mainline | 16 | 41,089m | n/a | 24" | Clay / Glacial Till | Jetted |
City of Leduc, AB - Potable Water Mainline | 10 | 16,870m | n/a | 8" | Clay / Glacial Till | Jetted |